Utilization of resources including tower crane, installation gang, bar-fixing gang, concreting gang and carpenter gang in high-rise housing construction are analyzed by using simulation, and the construction process of 6-day cycle is simulated.

 
  • 采用系统仿真技术分析高层住宅施工中资源的利用率,包括塔吊、安装组、钢筋绑扎组,混凝土浇注组和木工组。